General Project Information:

The energy infrastructure of Yandakly-Agyz village includes a 35/10 kV substation equipped with two 6,300 kVA power transformers, providing a total installed capacity of 12.6 MVA.
The substation provides voltage transformation from 35 kV to 10 kV and distribution of electrical power to consumers in the area.

Location:

Ahal Province, Turkmenistan

Scope of Work:

The project included civil, electrical installation, and commissioning works at the 35/10 kV substation with a total installed capacity of 12.6 MVA.

Civil and Electrical Installation Works:

  • Site preparation and construction of equipment foundations; 
  • Installation of two 35/10 kV, 6,300 kVA power transformers; 
  • Installation of 35 kV and 10 kV equipment; 
  • Laying and connection of power and control cables; 
  • Electrical connections and installation of the grounding system. 

Testing and Commissioning:

  • Electrical testing of the power transformers and 35/10 kV equipment; 
  • Inspection of cable and electrical connections and the grounding system; 
  • Functional testing of protection and control systems; 
  • Commissioning works and preparation of the substation for operation.